It has engaged Trant Engineering to develop a plan for their design, supply and installation.
SWS needed a number of these planned outputs by 31 March 2022 to meet the National Environment Programme (NEP) deadline.
Each EDM installation required a bespoke design to suit the existing infrastructure, creating a challenge for Trant andits electrical sub-contractors GA Electrical Services, SRE Services and telemetry specialists Multiform Technologies.
“We completed 54 installations in eight weeks to meet the 31 March deadline and are well on the way to completing all of the AMP7 requirements”, says Katie Kerr, Trantproject manager.
“We have been working on EDM with Trant since 2016 when the Environment Agency first introduced the programme,” says SWSproject manager Angus Cramp, “and Trant have always supported SWS to meet the deadline year on year”.