Sulzer moves and refurbishes 180-tonne welder for Tata Steel19 July 2018

The 180-tonne flash butt welder was moved The 180-tonne flash butt welder was moved from the Port Talbot works to the site in Llanwern

The Avonmouth Service Center of Sulzer has recently completed a project for Tata Steel that required a flash butt welder that was originally located in Port Talbot, to be dismantled, refurbished, relocated and commissioned on a pickling line in the Llanwern Works.

The flash butt welder weighs in excess of 180 tonnes, is positioned at the start of the pickling line and is used to join two rolls of steel together before continuing along the pickling line.

The initial part of the project was to dismantle the welder into modules to allow it to be transported by road to Sulzer's Avonmouth Service Center where it was fully dismantled and inspected to perform a complete appraisal.

The findings and recommendations were then communicated to allow the customer to take a decision on the viability of the refurbishment project.

One major design change was to the machine handling and control systems, which had to be reconfigured due to the steel strip flow being in the opposite direction in Llanwern. A completely new electrical wiring system and software was installed along with all new hydraulic and pneumatic piping.

In addition, new hydraulic valve stands with upgraded hydraulic pumps were also incorporated into the refurbished machine.

While this work was being completed in Avonmouth, in Llanwern the existing machine had to be removed to install new foundations in preparation for the arrival of the refurbished welder.

Careful coordination between Sulzer and Tata Steel ensured that the site would be ready and the project timetable would be maintained.

With the upgrades complete, the entire welder was reassembled at Sulzer Avonmouth to ensure that all the modifications had been successful and that the operation of the machine met the required Operational Engineering Standard. The fully functioning welder was then dismantled into modules for the final time for the short journey across the Severn Estuary before being reassembled in the Llanwern Works.

The Sulzer engineers completed the assembly and the connections with the rest of the production line before functional testing and initial welds were completed. Full production took less than two weeks following delivery to the site.

Adam Offord

Related Websites
http://www.dmaeuropa.com/tabid/3546/ItemId/5542/default.aspx?Uid=f02zaV84FUWGpQRkKZl3Og&ref=4995

Related Companies
Sulzer
Tata Steel

This material is protected by MA Business copyright
See Terms and Conditions.
One-off usage is permitted but bulk copying is not.
For multiple copies contact the sales team.