Dry-docking of LNG vessel includes major service for essential boil-off gas compressor16 December 2021
Burckhardt Compression has delivered a comprehensive overhaul service for Teekay LNG, a marine transportation company. As part of a long-term service agreement (LTSA) between the two companies, extensive planning and project management have ensured the time-critical project was completed on time, despite the extraordinary challenges of the COVID pandemic, and with a perfect safety record.
Part of Teekay’s LNG fleet, which is equipped with dual-fuel propulsion systems that use boil-off gas for fuel, transports energy supplies around the world. Each of these vessels is equipped with a Laby-GI BOG compressor that supplies fuel to the main and auxiliary engines as well as the reliquefication system and the gas combustion unit. After five years in operation, the compressor on the "Creole Spirit" was due for a scheduled maintenance inspection during dry-dock in Singapore.
Dry-dock maintenance projects are planned years in advance. With hundreds of specialist technicians and engineers working for dozens of suppliers, precision coordination by all those involved is essential. The resources involved and the scale of these projects mean that everyone has to deliver their part perfectly for the on-time completion of the whole scheme.
The Burckhardt Compression team planned and coordinated the numerous groups of contractors working on the compressor skid in the confines of the compressor machinery room (CMR) to ensure optimum working safety and efficiency. As the only BOG compressor on board, it is a crucial piece of equipment and the maintenance project was essential for continued availability.
Thanks to more than a year’s planning, the service ran with Swiss precision and was completed within the 13 days allotted, ensuring the complete dry-dock programme was also accomplished on time and without any safety incidents. Preparations included tailor-made packing cases for all the parts that were shipped to the Singapore Service Centre to ensure safe transportation. Burckhardt Compression’s on-site engineers were also able to quickly provide a solution to additional components of the control system that needed to be replaced.
Operations Engineer
Related Companies
Burckhardt Compression UK Ltd
This material is protected by MA Business copyright
See Terms and Conditions.
One-off usage is permitted but bulk copying is not.
For multiple copies
contact the sales team.