Dounreay destroys major atomic research hazard 11 April 2012
Dounreay has completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.
A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the Dounreay plant's original experimental fast breeder reactor.
The coolant – an alloy of sodium and potassium (NaK) - was a major chemical and radiological hazard. Around 1,000 trillion becquerels of caesium-137 was removed from the coolant during the chemical process that turned the 57 tonnes of liquid metal into 20,000 tonnes of salty water and took four years to complete.
"This is a tremendous achievement and another example of how the highly skilled Dounreay workforce is delivering a world-class clean-up operation at one of the most complex nuclear sites in Europe," says Scotland's Cabinet Secretary for the Environment Richard Lochhead, who saw the last batches being processed.
"This was very high on the list of hazards we wanted reduced across our whole estate," comments Nigel Lowe, head of the NDA's (Nuclear Decommissioning Agency) Dounreay programme. "It's a significant achievement for Dounreay and joins a long list of examples whereby the site has delivered on key objectives and technical challenges."
The reactor, which was built in the 1950s, was one of only two ever built in Britain to run on liquid metal. Two cooling circuits connected by heat exchangers were filled with more than 161,000 litres of liquid metal. More than 100,000 litres of NaK from the secondary circuit was destroyed when the reactor shut down in 1977.
Work on the primary circuit – a labyrinth of pipes 9km in length – stopped in the early 1980s when higher levels of radioactive contamination were detected. The open vent design of the fuel cladding had allowed the liquid metal to come into direct contact with the fuel, contaminating the primary coolant with huge levels of soluble radioactive caesium.
Lowe explains that the high level of radioactive contamination added to the chemical hazard of alkali metal that reacts in contact with air or water. Hence, its destruction remained on hold until a decade ago, when work started on the clean-up plant, which was designed to lift the liquid metal in small batches, neutralise the alkalinity with acid and extract the caesium via ion exchange.
In September 2007, the first of 354 batches was lifted from the reactor. Each batch underwent chemical neutralisation to convert the alkali metal to a salty water before being passed through ion exchange columns that trapped the caesium.
Designers originally thought the plant would decontaminate the effluent by a factor of 1000. However, decontamination rates of up to 4 million were achieved during the operation, reducing levels of radioactivity in the effluent to below the limit of detection.
The resin columns used to trap the caesium will now be cemented up and managed as higher-activity waste.
"It's been a fantastic achievement by the whole team to deliver this milestone a year ahead of schedule and to higher environmental standards than anyone thought possible at the design stage," states Andy Swan, engineer in charge of reactor decommissioning.
"This stuff was highly volatile and highly radioactive. The chemical and radiological hazards combined to make this a real danger to the workers involved, so we needed to be certain they were protected at every step of the process until the hazard was destroyed. Their safety record throughout this operation was excellent," he adds.
With the reactor vessel empty of liquid metal, attention will now turn to cleansing residual traces from the primary circuit pipework and destroying small pockets in other vessels. When complete, a robotic arm will reach into the reactor vessel and begin removing the burst fuel pin and almost 1,000 breeder elements still positioned around the plant core.
Brian Tinham
Related Companies
Dounreay Site Restoration Ltd
This material is protected by MA Business copyright
See Terms and Conditions.
One-off usage is permitted but bulk copying is not.
For multiple copies
contact the sales team.